Construct 3 buildings (9 units) Use Class E(g)(iii) employment starter units
Land Off Giltway Giltbrook
Minutes:
Construct 3 buildings (9 units) Use Class E(g)(iii) employment starter units
Land Off Giltway Giltbrook
The application was brought to the Committee as the applicant is Broxtowe Borough Council.
There were no late items.
There were no public speakers for this item.
The Committee opened the debate, which covered that a revised design for the construction of the new footpath including a retaining wall, rather than gabion wall construction had been submitted. It was considered that the principle of employment units were acceptable in this location.
RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission subject to:
1.The development hereby permitted shall be commenced before the expiration of three years beginning with the date of this permission.
Reason: To comply with S91 of the Town and Country Planning Act 1990 as amended by S51 of the Planning and Compulsory Purchase Act 2004.
2.The development hereby permitted shall be carried out in accordance with drawings received by the Local Planning Authority on the following dates:
• Location plan No. 13
• Proposed site section E-E No. 05
• Proposed plans and section unit 1 No. 07
• Proposed elevations unit 1 No. 08
• Proposed plans and section unit 2 No. 09
• Proposed elevations unit 2 No. 10
• Proposed plans and section unit 3 No. 11
• Proposed elevations unit 3 No. 12
(Received by the Local Planning Authority 24/09/26)
• Proposed site plan No. 01 A
• Proposed site plan (public right of way and levels) No. 03 B
• Proposed site section D-D No. 04 C
• Proposed site plan - northern path levels & gradients No. 14
(Received by the Local Planning Authority 09/10/26)
• Proposed site-scale elevations No. 06 C
(Received by the Local Planning Authority 13/10/26)
Reason: For the avoidance of doubt.
3.No part of the development hereby approved shall commence until a detailed surface water drainage scheme based on the principles set forward by the approved Flood Risk Assessment (FRA) and Drainage Strategy, has been submitted to and approved in writing by the Local Planning Authority in consultation with the Lead Local Flood Authority. The scheme shall be implemented in accordance with the approved details prior to completion of the development. The scheme to be submitted shall:
• Demonstrate that the development will use Sustainable Drainage Systems (SuDS) as a primary means of surface water management. Design should be in accordance with CIRIA C753, Policy F8 of the National Planning Policy Framework (2026) and the National Standards for Sustainable Drainage Systems (SuDS) 2025, applying a ‘SuDS approach’, so that:
- The surface water drainage system should incorporate attenuation at multiple points across the development, rather than a single attenuation feature located prior to the point of discharge, unless justification is provided.
- At least the first 5mm of rainfall for the majority of rainfall events does not result in runoff from the site to surface waters or piped drainage systems.
- Surface water and groundwater is protected by managing the quality of the surface water runoff to adequately address water quality risks from the development.
- Benefits are maximised for amenity through the creation of multi-functional places and landscapes.
- Benefits are maximised for biodiversity throughout the development lifecycle.
Evidence shall be provided that the approach to managing runoff from ‘everyday’ rainfall has been developed alongside and in support of the management of runoff quality and the delivery of amenity and biodiversity benefits.
Note: The LLFA does not consider oversized pipes or box culverts as sustainable drainage.
• Limit the discharge generated by all rainfall events up to the 100 year plus 40% (climate change) critical rain storm to QBar rates for the developable area.
• Provide details of a proven outfall from site in accordance with the drainage hierarchy. The following options should be considered in order of preference, as stated in the National Standards for Sustainable Drainage Systems (SuDS) 2025:
- Priority 1: collected for non-potable use
- Priority 2: infiltrated to ground
- Priority 3: discharged to an above ground surface water body
- Priority 4: discharged to a surface water sewer, or another piped surface water drainage system
- Priority 5: discharged to a combined sewer
• Provide detailed design (plans, network details, calculations and supporting summary documentation) in support of any surface water drainage scheme, including details on any attenuation system, the outfall arrangements and any private drainage assets.
Calculations should demonstrate the performance of the designed system for a range of return periods and storm durations inclusive of the 1 in 1 year, 1 in 30 year and 1 in 100 year plus climate change return periods.
- No surcharge shown in a 1 in 1 year.
- No flooding shown in a 1 in 30 year.
- For all exceedance to be contained within the site boundary without flooding properties in a 100 year plus 40% storm.
• Evidence to demonstrate the viability (e.g Condition, Capacity and positive onward connection) of any receiving watercourse to accept and convey all surface water from the site.
• Details of STW approval for connections to existing network and any adoption of site drainage infrastructure.
• Evidence of approval for drainage infrastructure crossing third party land where applicable.
• Provide a surface water management plan demonstrating how surface water flows will be managed during construction to ensure no increase in flood risk off site.
• Evidence of how the on-site surface water drainage systems shall be maintained and managed after completion and for the lifetime of the development to ensure long term effectiveness.
Reason: To ensure the development has sufficient surface water management in accordance with the aims of policy 1 of the Part 2 Local Plan (2019), Policy 1 of the Aligned Core Strategy (2014) and the NPPF (2026).
4.Statutory Biodiversity - Deemed Condition
Biodiversity Net Gain (BNG) of 10% for developments is a mandatory requirement in England under the Environment Act 2021.
The effect of the relevant paragraphs of Schedule 7A to the Town and Country Planning Act 1990 is that planning permission granted for the development of land in England is deemed to have been granted subject to the condition (the biodiversity gain condition) that development may not begin unless:
a. a Biodiversity Gain Plan has been submitted to the planning authority, and
b. the planning authority has approved the plan.
The planning authority, for the purposes of determining whether to approve a Biodiversity Gain Plan if one is required in respect of this permission would be Broxtowe Borough Council.
Key Requirements:
A Biodiversity Gain Plan (BGP) must be submitted to the Local Planning Authority, in writing no earlier than the day after planning permission has been granted and should be in accordance with the BNG Metric received by the Local Planning Authority on 21 September 2026, prepared by Elton Ecology Ltd.
The biodiversity gain plan must include:
(a) information about the steps taken or to be taken to minimise the adverse effect of the development on the biodiversity of the onsite habitat and any other habitat;
(b) the pre-development biodiversity value of the onsite habitat;
(c) the post-development biodiversity value of the onsite habitat;
(d) any registered offsite biodiversity gain allocated to the development and the biodiversity value of that gain in relation to the development;
(e) any biodiversity credits purchased for the development; and
(f) any such other matters as the Secretary of State may by regulations specify.
When calculating the post-development biodiversity value of a habitat, the planning authority can only take into account an increase in biodiversity value post development where it is satisfied that the habitat creation or enhancements delivering the increase will be maintained for at least 30 years after the development is completed. This must be secured either by a planning condition, planning obligation, or conservation covenant.
Template available here;
https://www.gov.uk/government/publications/biodiversity-gain-plan
Reason: To ensure the development delivers a biodiversity net gain on or off site in accordance with the relevant paragraphs of Schedule 7A of the Town and Country Planning Act 1990.
5.No development shall commence until details of any necessary ground compaction, piling or other penetrative foundation design have been submitted to and approved in writing by the Local Planning Authority including details of any mitigation measures to minimise the effects of noise and vibration on surrounding occupiers. The development shall be implemented in accordance with the approved details.
Reason: To protect nearby occupants from excessive construction noise and vibration in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
6.Details of floodlighting of the site shall be submitted to and approved in writing by the Local Planning Authority prior to commencement of development. The development shall be constructed only in accordance with the approved details.
Reason: In the interests of the amenities of nearby residents and in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
7.No development hereby permitted shall commence until wheel washing facilities have been installed on the site in accordance with details first submitted to and approved in writing by the LPA. The wheel washing facilities shall be maintained in working order at all times and shall be used by any vehicle carrying mud, dirt or other debris on its wheels before leaving the site so that no mud, dirt or other debris is discharged or carried on to a public road.
Reason: In the interests of highway safety and in accordance with the aims of Policy 17 of the Part 2 Local Plan (2019).
8.No development within the full planning permission phase hereby approved shall take place until a Construction Method Statement (CMS) / Construction Environmental Management plan (CEMP) has been submitted to and approved in writing by the Borough Council. The statement shall include:
a) The means of access for construction traffic;
b) parking provision for site operatives and visitors;
c) the loading and unloading of plant and materials;
d) the storage of plant and materials used in construction / demolition of the development;
e) a scheme for the recycling/disposal of waste resulting from
construction works; and
f) details of fugitive dust and construction noise control to be used during the construction phase.
The approved statement shall be adhered to throughout the construction period.
Reason: In the interests of the amenities of nearby residents and in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
9.No development above slab level shall commence until a landscaping scheme has been submitted to and approved by the Local Planning Authority. This scheme shall include the following details:
(a) numbers, types, sizes and positions of proposed trees and shrubs
(b) proposed boundary treatments
(c) proposed hard surfacing treatment
(d) proposed external lighting details
(e) planting, seeding/turfing of other soft landscape areas
The approved scheme shall be carried out strictly in accordance with the agreed details.
Reason: In the interests of visual amenity and in accordance with Policies 17 and 31 of the Part 2 Local Plan (2019) and Policies 10 and 17 of the Aligned Core Strategy (2014).
10.No development above slab level shall commence until written and illustrative details of the siting, design and finished levels of the new footpath and retaining wall have been submitted to and approved in writing by the Local Planning Authority. Details must include the proposed surfacing and long-term maintenance of the new footpath. No commercial unit shall be occupied until the new footpath has been provided in accordance with the approved details.
Reason: To ensure the construction of the new footpath is safe for future users in accordance with the aims of Policy 17 of the Part 2 Local Plan (2019) and policy TR8 of the NPPF (2026).
11.Prior to any construction above foundations level, a scheme of biodiversity enhancement shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include, as a minimum, the incorporation of features within the development for roosting bats, bees and nesting swifts. The enhancement scheme shall be implemented in accordance with the agreed details as construction proceeds and completed prior to the first occupation of the development.
Reason: In the interests of securing biodiversity enhancements in accordance with Policy 31 of the Part 2 Local Plan (2019) and Policy 17 of the Aligned Core Strategy Part 1 Local Plan (2014).
12.No part of the development hereby permitted shall be brought into use until the parking, turning and servicing areas are surfaced in a bound material with the parking bays clearly delineated in accordance with drawing number 2026-2198 02a. The parking, turning and servicing areas shall be maintained in the bound material for the life of the development and shall not be used for any purpose other than the parking, turning and loading and unloading of vehicles.
Reason: In the interests of highway safety and in accordance with the aims of Policy 17 of the Part 2 Local Plan (2019).
13.No construction or site preparation work in association with this permission shall be undertaken outside the hours of 08:00-18:00 Monday to Friday, 08:00-13:00 on Saturdays and at no time on Sundays or Bank Holidays.
Reason: In the interests of the amenities of nearby residents and in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
14.No removal of shrubs and scrub shall take place between 1st March and 31st August inclusive unless a survey to assess the nesting bird activity on the site during this period and a scheme to protect the nesting birds has first been submitted to and approved in writing by the Local Planning Authority. No shrubs or scrub shall be removed between 1st March and 31st August inclusive other than in accordance with the approved bird nesting protection scheme.
Reason: In the interests of securing the protection of protected species in accordance with Policy 31 of the Part 2 Local Plan (2019) and Policy 17 of the Aligned Core Strategy (2014).
15.All plant, machinery and equipment (including fans, ducting and external openings) to be used by reason of the granting of this permission shall be so installed, maintained and operated so as to prevent the transmission of noise and vibration into any premises either attached to, or beyond the red line of the application site to which the application refers.
Reason: To protect the amenity of neighbouring residents in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
16.The total rating level resulting from the use of any plant, machinery or equipment hereby installed pursuant to this permission, shall not exceed the existing background sound level when measured according to British Standard BS4142:2014, at a point one metre external to the nearest noise sensitive premises.
Reason: To protect existing residents from excessive plant noise in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
17.The premises shall not be used except between 07.30-21.00 hours Monday to Saturday and at no time on Sundays, Bank Holidays and other public holidays without the prior agreement in writing of the Local Planning Authority.
Reason: To protect the amenity of neighbouring residents in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
18.Deliveries by commercial vehicles shall not be permitted except between 07.30-21.00 hours Monday to Saturday and at no time on Sundays, Bank Holidays and other public holidays without the prior agreement in writing of the Local Planning Authority.
Reason: To protect the amenity of neighbouring residents in accordance with the aims of Policy 19 of the Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014).
Notes to Applicant
1.The Council has acted positively and proactively in the determination of this application by working to determine it within the agreed determination timescale.
2.As this permission relates to the creation of new units, please contact the Council's Street Naming and Numbering team: 3015snn@broxtowe.gov.uk to ensure an address or addresses are created. This can take several weeks and it is advised to make contact as soon as possible after the development commences. A copy of the decision notice, elevations, internal plans and a block plan are required. For larger sites, a detailed site plan of the whole development will also be required.
3.If any coal mining features are unexpectedly encountered during development, this should be reported immediately to the Coal Authority on 0800 288 4242. Further information is available on the Coal Authority website at: www.gov.uk/government/organisations/the-coal-authority