APPLICATION NUMBER/FUL

Meeting: 04/12/2024 - Planning Committee (Item 36)

36 24/00669/REG pdf icon PDF 1 MB

Construct two/three storey building serving mixed uses with associated landscaping and parking

Car Park ,Victoria Street, Stapleford Nottinghamshire NG9 7AP

Minutes:

Construct two/three storey building serving mixed uses with associated landscaping and parking

Car Park ,Victoria Street, Stapleford Nottinghamshire NG9 7AP

 

The application was brought before Committee as the Council was the landowner and applicant.

 

There were a number of late items, including changes to condition 4 and condition 8.  It was noted that the correct wording for condition 8 was as follows:

 

No sound reproduction, air conditioning units, or amplification equipment (including public address systems, loud speakers, etc) which is audible at the site boundary shall be installed or operated on the site without the prior written approval of the Local Planning Authority.

 

Tina McInerney, objecting and Councillor J W McGrath, Ward Member, made representation to the Committee prior to the general debate.

 

The Committee gave due regard to the information before it and the debate commenced with particular reference to the opening times for the public toilets and the loss of parking.  It was also noted that the proposed development represented an investment in Stapleford Town Centre that would benefit the local economy and provide opportunities for small, local enterprises.

 

RESOLVEDthat the Head of Planning and Economic Development be given delegated authority to grant planning permission, including the changes to condition 4 and condition 8, subject to:

 

(i)         Prior completion of an agreement under Section 106 of the Town and Country Planning Act 1990 to secure the provision of Biodiversity Net Gain

(ii)        the following conditions:

 

1.

Condition:

 

The development hereby permitted shall be commenced before the expiration of three years beginning with the date of this permission.

 

Reason:

 

To comply with S91 of the Town and Country Planning Act 1990 as amended by S51 of the Planning and Compulsory Purchase Act 2004.

 

 

2.

Condition:

 

The development hereby permitted shall be carried out in accordance with the plans

 

Received by the Local Planning Authority on 1 October 2024:

 

    Existing Site Plan and Elevation ref: 3572-MAB-00-00-D-A-0101 rev: P01

    Sections – Stage 3 ref: 3572-MAB-00-ZZ-D-L-4410 rev: P01

    Proposed Ground Floor Plan ref: 3572-MAB-ZZ-00-D-A-0120 rev: P05

    Proposed First Floor Plan ref: 3572-MAB-ZZ-01-D-A-0121 rev: P02

    Proposed Second Floor Plan ref: 3572-MAB-ZZ-02-D-A-0122 rev: P02

    Proposed Roof Plan ref: 3572-MAB-ZZ-RF-D-A-0123 rev: P01

    Proposed Elevations ref: 3572-MAB-ZZ-ZZ-D-A-0160 rev: P02

    Proposed Elevations ref: 3572-MAB-ZZ-ZZ-D-A-0161 rev: P03

    Proposed Elevations ref: 3572-MAB-ZZ-ZZ-D-A-0162 rev: P02

    Proposed Sections ref: 3572-MAB-ZZ-ZZ-D-A-0170 rev: P02

    Proposed Sections ref: 3572-MAB-ZZ-ZZ-D-A-0171 rev: P02

    Proposed Sections ref: 3572-MAB-ZZ-ZZ-D-A-0172 rev: P02

 

Received by the Local Planning Authority on 4 October 2024:

 

·       Block Plan ref: 3572-MAB-00-00-D-L-0103 rev: P01

 

Received by the Local Planning Authority on 15 November 2024:

 

·       Landscape Masterplan Stage 3 ref: 3572-MAB-00-00-D-L-4000 rev: P03

 

Reason:

 

For the avoidance of doubt.

 

3.

 

Condition:

No development shall commence until a remediation scheme to ensure safe development and mitigate any potential risks from asbestos containing materials in the ground has been submitted to and approved in writing by the Local Planning Authority. The agreed remediation scheme shall be implemented in full during development. 

In the event that  ...  view the full minutes text for item 36