Decision Maker: Bramcote Bereavement Services Joint Committee
Decision status: For Determination
Is Key decision?: No
To provide the Joint Committee with an update
on the progress with regards replacement cremators.
The Joint Committee were provided with an update on the progress with regards the replacement cremators project.
It was noted that the project was currently 21 days behind schedule.
Facultative Technologies (FT) reported during project meetings that they planned to install the first cremator November 2024. Due to manufacturing constraints within FT’s business further delays have resulted. The revised Installation date would now commence 1 January 2025.
Report author: Richard Mott
Publication date: 14/11/2024
Date of decision: 24/10/2024
Decided at meeting: 24/10/2024 - Bramcote Bereavement Services Joint Committee