CAPITAL PROGRAMME 2020/21 -NEW BUILD OAKFIELD ROAD

Decision Maker: Finance and Resources Committee

Decision status: Recommendations Approved

Decisions:

The Committee considered the allocation of an additional £65,000 from the 2020/21 HRA Capital Programme to build 5 highly energy efficient flats.

         

It was noted that the funding was mainly related to the lack of capacity with the existing electrical network at Oakfield Road and the subsequent upgrade work required by Western Power, at a cost of £46,000.   

 

          RESOLVED that the 2020/21 Capital Programme be amended so that the budget for the New Build – Oakfield Road scheme be increased from £700,000 to £765,000 with the additional £65,000 cost met from HRA capital receipts.

 

Publication date: 29/04/2021

Date of decision: 10/12/2020

Decided at meeting: 10/12/2020 - Finance and Resources Committee

Accompanying Documents: