    Members received an update on progress made with regard to The Square  Phase 2 in Beeston. It was noted that the Christmas 2020 opening was on target.  Contracts had been exchanged with The Arc cinema and the overall project was  proceeding well. The Committee was informed by the Deputy Chief Executive that the item would be discussed in more depth later in the agenda as there were exempt items to be considered.

 

RESOLVED to continue to delegate to the Deputy Chief Executive all key approvals, in consultation with the cross-party Project Board, and subject to the overall project cost remaining within the financial limits already set or subsequently changed by the Finance and Resources Committee and/or Full Council as appropriate.

 

Publication date: 30/07/2020

Date of decision: 02/10/2019

Decided at meeting: 02/10/2019 - Policy and Performance Committee