Update on Replacement Cremators

Decision Maker: Bramcote Bereavement Services Joint Committee

Decision status: For Determination

Is Key decision?: No

Purpose:

To provide the Joint Committee with an update on the progress with regards replacement cremators.

Decisions:

The Joint Committee were provided with an update on the progress with regards the replacement cremators project.

 

It was noted that the project was currently 21 days behind schedule.

 

Facultative Technologies (FT) reported during project meetings that they planned to install the first cremator November 2024. Due to manufacturing constraints within FT’s business further delays have resulted. The revised Installation date would now commence 1 January 2025.

 

Report author: Richard Mott

Publication date: 14/11/2024

Date of decision: 24/10/2024

Decided at meeting: 24/10/2024 - Bramcote Bereavement Services Joint Committee